Contractor Environmental Site Representative for Wyong Road intersection upgrade at Enterprise Drive

In 2016 Umwelt provided a contractor Environmental Site Representative (ESR) to BMD Constructions, the principal contractor for a $28 million Roads and Maritime Services (RMS) Upgrade Project. Umwelt was approved by RMS to provide environment and community services including:

  • Monitor and review compliance to RMS specifications and guidelines.
  • Undertake environmental inspections.
  • Implement the site’s Construction Environmental Management Plan (CEMP) and associated management plans.
  • Undertake environmental monitoring in accordance with the CEMP, relevant management plans and RMS specifications.
  • Develop and regularly update the Erosion and Sediment Control Plans (ESCPs).
  • Overall responsibility for the establishment, management and maintenance of erosion and sediment controls across the site.
  • Liaise with RMS and relevant authorities on environmental and community matters.
  • Act as the site’s community liaison representative and distribute community notifications and project updates as required.

project_oct_2016_b